HACKER SAFEにより証明されたサイトは、99.9%以上のハッカー犯罪を防ぎます。
カート(0

PMI PMI-SP 問題集

PMI-SP

試験コード:PMI-SP

試験名称:PMI Scheduling Professional

最近更新時間:2025-03-29

問題と解答:全326問

PMI-SP 無料でデモをダウンロード:

PDF版 Demo ソフト版 Demo オンライン版 Demo

追加した商品:"PDF版"
価格: ¥6599 

無料問題集PMI-SP 資格取得

質問 1:
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410 What is the schedule variance (SV) of the project at the current point of time?
A. -110
B. -25
C. +25
D. +110
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 2:
You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?
A. Crashing increases project costs.
B. Crashing is a top-down approach to project completion.
C. Crashing always increases project risks.
D. Crashing restricts resource utilization.
正解:A
解説: (Topexam メンバーにのみ表示されます)

質問 3:
Don is the project manager of the NQP project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. Which of the following documents should Don refer to, for the information on the activities and the regulations?
A. Risk management plan
B. Activity list
C. Risk register
D. Activity list and attributes
正解:D
解説: (Topexam メンバーにのみ表示されます)

質問 4:
You are the project manager of the NHQ Project. Management has told you that resource leveling will be enforced on your project, but they still want you to complete the project by July 2. With the current resources you have and the resource leveling imposed, you would not be able to finish by the constraint. What document should you update to address this situation?
A. Project activity resource requirements
B. Project scope
C. Project schedule management plan
D. Project charter
正解:A
解説: (Topexam メンバーにのみ表示されます)

質問 5:
Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?
A. Corrective action
B. Risk response
C. Team development
D. Risk mitigation
正解:A
解説: (Topexam メンバーにのみ表示されます)

質問 6:
Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.
A. Resource leveling heuristic
B. Assumption
C. Constraint
D. Execution variance analysis
正解:A,C
解説: (Topexam メンバーにのみ表示されます)

PMI PMI-SP 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Collect resource information and updates via reports, timesheets, meetings, inspections
  • Develop the project resource breakdown structure (RBS)
トピック 2
  • Perform schedule risk analysis using quantitative tools or techniques
  • Analyze major milestones against statement of work (SOW)
トピック 3
  • Adjust schedule model based upon resource availability
  • Establish the Performance Measurement Baseline (PMB)
トピック 4
  • Perform schedule analysis and audit, on in-house and subcontractor schedules
  • Provide information about project scheduling objectives and goals
トピック 5
  • Establish project schedule configuration management policies and procedures incorporating best practices
  • Align schedule with the overall program plan or integrated master plan (IMP)
トピック 6
  • Obtain a consensus of the project customer, sponsor, project manager
  • Update the schedule model and document schedule baseline changes

参照:http://www.pmi.org/certification/scheduling-professional-sp/pmi-sp-exam-prep.aspx

一年間の無料更新サービスを提供します

君が弊社のPMI PMI-SPをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたPMI PMI-SPをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のPMI PMI-SPを持っていることを保証します。

弊社は無料PMI PMI-SPサンプルを提供します

お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料PMI-SPサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのPMI-SP問題集は自分に適するかどうか判断して購入を決めることができます。

PMI-SP試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。

安全的な支払方式を利用しています

Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のPMI-SP問題集は全部Credit Cardで支払われることができます。

領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。

弊社は失敗したら全額で返金することを承諾します

我々は弊社のPMI-SP問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のPMI PMI-SPを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。

TopExamは君にPMI-SPの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。

弊社のPMI PMI-SPを利用すれば試験に合格できます

弊社のPMI PMI-SPは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はPMI-SP問題集の質問と答えが間違いないのを保証いたします。

PMI-SP無料ダウンロード

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のPMI PMI-SPを利用すれば、君は一回で試験に合格できます。

PMI-SP 関連試験
PgMP - Program Management Professional (PgMP)
連絡方法  
 [email protected] サポート

試用版をダウンロード

人気のベンダー
Apple
Avaya
CIW
FileMaker
Lotus
Lpi
OMG
SNIA
Symantec
XML Master
Zend-Technologies
The Open Group
H3C
3COM
ACI
すべてのベンダー
TopExam問題集を選ぶ理由は何でしょうか?
 品質保証TopExamは我々の専門家たちの努力によって、過去の試験のデータが分析されて、数年以来の研究を通して開発されて、多年の研究への整理で、的中率が高くて99%の通過率を保証することができます。
 一年間の無料アップデートTopExamは弊社の商品をご購入になったお客様に一年間の無料更新サービスを提供することができ、行き届いたアフターサービスを提供します。弊社は毎日更新の情況を検査していて、もし商品が更新されたら、お客様に最新版をお送りいたします。お客様はその一年でずっと最新版を持っているのを保証します。
 全額返金弊社の商品に自信を持っているから、失敗したら全額で返金することを保証します。弊社の商品でお客様は試験に合格できると信じていますとはいえ、不幸で試験に失敗する場合には、弊社はお客様の支払ったお金を全額で返金するのを承諾します。(全額返金)
 ご購入の前の試用TopExamは無料なサンプルを提供します。弊社の商品に疑問を持っているなら、無料サンプルを体験することができます。このサンプルの利用を通して、お客様は弊社の商品に自信を持って、安心で試験を準備することができます。