質問 1:
The program manager leads a medical billing system integration program for company A. a health services provider Company A acquires smaller company X. which delivers health services strategically aligned with company A Company X uses a different billing approach than company A. Company A's chief information officer (CIO) seeks counsel on which solution would be the better option moving forward requesting the program manager's assistance.
How should the program manager respond to the ClO's request1?
A. Gather the costs and benefits associated with each option and recommend the appropriate solution defining why the selected approach is better
B. Find similar examples of the preferred approach and ask the project teams to document why the preferred approach is better
C. Conduct a thorough stakeholder analysis and develop a program management plan to implement the appropriate solution for both companies.
D. Document the resources required to implement the recommended solution and demonstrate how this solution will save the company money
正解:A

質問 2:
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy However before the program is formally initialed, this strategy must be aligned with the organization's strategic goals and objectives.
What should the program manager develop first?
A. Program risk management plan
B. Program's risk threshold
C. Program risk and issue governance forum
D. Program resource management plan
正解:B

質問 3:
Telecommunications cabling (e.g., voice, data, video, security, audio, control) can be damaged during the construction phases of rough-in, drywall installation, and during the siding of the exterior. For these reasons, telecommunications cabling shall be acceptance tested. Acceptance testing includes visual examination and verification of all cabling and qualification of copper cabling for data cabling or certification of copper or optical fiber cabling for data cabling. Verification testing is generally performed in which two of the following steps? (Choose two.)
A. Post the acceptance of the construction contract once the Project Manager has approved this phase
B. During the trim-out stage of the cabling after painting
C. Post the implementation of the construction
D. Prior to the installation of insulation and drywall
E. Prior to the installation of the cable tray system for spurs, points that would or could damage the cable infrastructure
正解:B,D

質問 4:
A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?
A. Define the component protects business value in the benefits management plan
B. Initiate a program change request to close out the component project
C. Update the program roadmap to reflect completion of a key end-point objective
D. Update the program stakeholder engagement plan with stakeholders from the transition organization
正解:C

質問 5:
A telephone facility and an electrical facility are required in a tunnel. To reduce the effects of EMI and eliminate the need for additional shielding of the cables, where would each facility be placed?
A. On opposite sides of the tunnel
B. On the exterior of the tunnel
C. On the same sides of the tunnel
D. One on the top part and one on the bottom part of the same side of the tunnel
E. Together on the same pathway for easy access and maintenance
正解:A

質問 6:
When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)
A. Submit an alternate product in lieu of one that was previously submitted, even if it does not meet all of the contract requirements
B. Review the contract requirements and revise the submittal to comply with these requirements
C. Request a variance from the contract requirements from the client.
D. Document the reviewer's status and/or comments
E. Request a Change Order from the client for the extra work performed.
正解:A,C

質問 7:
An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding.
To ensure continued funding for the program, what should the program manager do next?
A. Review the program business case and the program's strategic alignment and long-term benefits with the program governance board.
B. Complete the benefits sustainment plan and update the benefits register
C. Present a revised ROl to the program sponsors based on the remaining investment.
D. Conduct a cost-benefit analysis to ensure the program sponsors understand the program's long-term benefits
正解:D

質問 8:
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?
A. Benefits register updates
B. Earned value (EV) report
C. Customer sign-off
D. Feedback and lessons learned
正解:D

安全的な支払方式を利用しています

Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のRCDDv14.1問題集は全部Credit Cardで支払われることができます。

領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。

弊社は失敗したら全額で返金することを承諾します

我々は弊社のRCDDv14.1問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のBICSI RCDDv14.1を利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。

BICSI RCDDv14.1 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Support ICT Bid
  • Tender Process: This segment examines your proficiency in creating and responding to RFPs
  • RFQs, managing RFIs, evaluating bids and tenders, and engaging in additional bidding-related activities.
トピック 2
  • Support ICT Installation Process: The final section measures skills such as how to create and assess submittals, contribute to material procurement, manage installation coordination, and carry out field engineering.
トピック 3
  • Design ICT Solutions: This substantial exam section assesses your capability to generate project documentation, plan for telecommunication spaces, collaborate with various disciplines, determine appropriate work area outlet placements, and specify requirements for grounding, bonding, and protection.
トピック 4
  • Define Scope of ICT Design: This portion of the exam evaluates your ability to determine the project's scope, create ICT system designs by relevant codes and standards,|cost and timeline projections, and evaluate existing conditions.

参照:https://www.bicsi.org/education-certification/certification/rcdd

TopExamは君にRCDDv14.1の問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。

弊社のBICSI RCDDv14.1を利用すれば試験に合格できます

弊社のBICSI RCDDv14.1は専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はRCDDv14.1問題集の質問と答えが間違いないのを保証いたします。

RCDDv14.1無料ダウンロード

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のBICSI RCDDv14.1を利用すれば、君は一回で試験に合格できます。

一年間の無料更新サービスを提供します

君が弊社のBICSI RCDDv14.1をご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたBICSI RCDDv14.1をお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のBICSI RCDDv14.1を持っていることを保証します。

弊社は無料BICSI RCDDv14.1サンプルを提供します

お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料RCDDv14.1サンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのRCDDv14.1問題集は自分に適するかどうか判断して購入を決めることができます。

RCDDv14.1試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。

RCDDv14.1 関連試験
INSTC_V7 - BICSI Installer 2 - Copper Exam
連絡方法  
 [email protected] サポート

試用版をダウンロード

人気のベンダー
Apple
Avaya
CIW
FileMaker
Lotus
Lpi
OMG
SNIA
Symantec
XML Master
Zend-Technologies
The Open Group
H3C
3COM
ACI
すべてのベンダー
TopExam問題集を選ぶ理由は何でしょうか?
 品質保証TopExamは我々の専門家たちの努力によって、過去の試験のデータが分析されて、数年以来の研究を通して開発されて、多年の研究への整理で、的中率が高くて99%の通過率を保証することができます。
 一年間の無料アップデートTopExamは弊社の商品をご購入になったお客様に一年間の無料更新サービスを提供することができ、行き届いたアフターサービスを提供します。弊社は毎日更新の情況を検査していて、もし商品が更新されたら、お客様に最新版をお送りいたします。お客様はその一年でずっと最新版を持っているのを保証します。
 全額返金弊社の商品に自信を持っているから、失敗したら全額で返金することを保証します。弊社の商品でお客様は試験に合格できると信じていますとはいえ、不幸で試験に失敗する場合には、弊社はお客様の支払ったお金を全額で返金するのを承諾します。(全額返金)
 ご購入の前の試用TopExamは無料なサンプルを提供します。弊社の商品に疑問を持っているなら、無料サンプルを体験することができます。このサンプルの利用を通して、お客様は弊社の商品に自信を持って、安心で試験を準備することができます。