質問 1:
Determine the correct formula and date for the late start for the Activity 11001:

A. LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024
B. LF of 1000 less 25 days equaling 16 Jan 2024
C. LF of 11001 less duration of 11001 equaling 16 Jan 2024
D. LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 2:
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

A. 06-11-02.
B. 06-18-02.
C. 06-04-02.
D. 06-05-02.
正解:D
解説: (Topexam メンバーにのみ表示されます)

質問 3:
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
A. 9001 and 6002 and 6002
B. 1000. 1001. and 6001
C. 1000 and 6001
D. 1001 and 6001
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 4:
Background
Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.
It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.
You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.
With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.
In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.
1. Pull the project team together and ensure everyone understands which activities are on the critical path.
Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.
2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.
3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.
4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.
Assignment
Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:
a. the current problem and potential impact(s);
b. each course of action, stating advantages and disadvantages as appropriate; c. your recommendations, properly supported.
Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).
While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.Take time to read the problem and consider what you want Evan to say. Good luck!
正解:
See the Explanation for complete Solution for this.
Explanation:
To: Desmond Rayburn, Director of Information ServicesFrom: Evan Marshal, Corporate SchedulerDate:
[Insert Current Date]Subject: Mitigation Plan for Project JP-114 Delays Current Problem and Potential ImpactsProject JP-114 has experienced schedule delays and cost overruns.
The project has expended $37,000 against a planned budget of $30,000 to date, exceeding the planned budget by 23%. Additionally, productivity issues have impacted critical path activities, further delaying progress.
With nine months remaining, failing to address these issues could result in penalties, further cost increases, and client dissatisfaction.
* Focus Existing Team on Critical Path with Periodic Overtime
* Advantages: Uses team familiarity; incurs a moderate budget increase (20%).
* Disadvantages: Risks resource strain and potential burnout if overtime is prolonged.
* Outsource Work to Consultants
* Advantages: Accelerates schedule by parallel work streams; minimizes internal team overtime.
* Disadvantages: Higher budget impact (up to 40%); requires effective integration of external deliverables.
* Mandatory Overtime (50-Hour Work Week)
* Advantages: Ensures rapid progress across the project.
* Disadvantages: Extremely high cost (60% increase); risks significant employee fatigue and declining morale.
* Continue as Is and Accept Late Delivery Penalties
* Advantages: No immediate resource strain.
* Disadvantages: Significant penalties (50% budget increase); damages stakeholder confidence and corporate reputation.
Courses of Action
RecommendationI recommend Option 1, combined with selective outsourcing (Option 2), to achieve the best balance of cost control and schedule recovery.
* Focus the internal team on critical path activities with targeted use of periodic overtime. This ensures efficient allocation of resources and minimizes strain while addressing the most urgent delays.
* Outsource select non-critical tasks to experienced consultants. This parallel effort reduces the workload on the internal team, limits overtime, and accelerates overall progress.
Rationale:This hybrid approach keeps the budget increase to approximately 30-35% while effectively addressing schedule delays. It balances cost efficiency, resource management, and stakeholder satisfaction.
Proper coordination will ensure smooth integration between internal and external teams.
ConclusionThis plan provides the most feasible path to bringing Project JP-114 back on track. It mitigates risks of extended delays while maintaining budget discipline. I am available for further discussions to outline a detailed implementation plan.
Best Regards,Evan MarshalCorporate Scheduler

質問 5:
Which statement is true?
A. Where compensability cannot be established, excusability is a given.
B. Where compensability can be established, excusabltity cannot be assumed.
C. Where compensability cannot be established, excusability is assumed.
D. Where compensability can be established, excusability is assumed.
正解:D
解説: (Topexam メンバーにのみ表示されます)

弊社は失敗したら全額で返金することを承諾します

我々は弊社のPSP問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のASIS PSPを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。

一年間の無料更新サービスを提供します

君が弊社のASIS PSPをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたASIS PSPをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のASIS PSPを持っていることを保証します。

ASIS PSP 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Physical Security Assessment: For ASIS Physical Security Professional (PSP) exam candidates, this topic measures the ability to craft a comprehensive physical security assessment plan. It evaluates skills in identifying critical assets, assessing threats, and quantifying organizational vulnerabilities, crucial for determining overall risk. This ensures that ASIS Physical Security Professionals can effectively analyze and mitigate potential security breaches, demonstrating their competency in safeguarding an organization’s physical infrastructure.
トピック 2
  • Implementation of Physical Security Measures: This topic covers skills such as conducting pre-bid meetings, developing procurement plans, and managing the implementation of security goods and services. Proficiency in these areas ensures that ASIS PSP exam candidates can oversee the deployment of physical security programs, maintaining operational integrity and meeting security objectives.
トピック 3
  • Application, Design, and Integration of Physical Security Systems: In this topic, ASIS Physical Security Professionals are tested on their expertise in designing and integrating physical security systems. This topic assesses their capability to establish performance requirements, choose appropriate security countermeasures, and create detailed project documentation.

参照:https://www.asisonline.org/globalassets/certification/documents/certification-handbook_final.pdf

TopExamは君にPSPの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。

安全的な支払方式を利用しています

Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のPSP問題集は全部Credit Cardで支払われることができます。

領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。

弊社のASIS PSPを利用すれば試験に合格できます

弊社のASIS PSPは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はPSP問題集の質問と答えが間違いないのを保証いたします。

PSP無料ダウンロード

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のASIS PSPを利用すれば、君は一回で試験に合格できます。

弊社は無料ASIS PSPサンプルを提供します

お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料PSPサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのPSP問題集は自分に適するかどうか判断して購入を決めることができます。

PSP試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。

連絡方法  
 [email protected] サポート

試用版をダウンロード

人気のベンダー
Apple
Avaya
CIW
FileMaker
Lotus
Lpi
OMG
SNIA
Symantec
XML Master
Zend-Technologies
The Open Group
H3C
3COM
ACI
すべてのベンダー
TopExam問題集を選ぶ理由は何でしょうか?
 品質保証TopExamは我々の専門家たちの努力によって、過去の試験のデータが分析されて、数年以来の研究を通して開発されて、多年の研究への整理で、的中率が高くて99%の通過率を保証することができます。
 一年間の無料アップデートTopExamは弊社の商品をご購入になったお客様に一年間の無料更新サービスを提供することができ、行き届いたアフターサービスを提供します。弊社は毎日更新の情況を検査していて、もし商品が更新されたら、お客様に最新版をお送りいたします。お客様はその一年でずっと最新版を持っているのを保証します。
 全額返金弊社の商品に自信を持っているから、失敗したら全額で返金することを保証します。弊社の商品でお客様は試験に合格できると信じていますとはいえ、不幸で試験に失敗する場合には、弊社はお客様の支払ったお金を全額で返金するのを承諾します。(全額返金)
 ご購入の前の試用TopExamは無料なサンプルを提供します。弊社の商品に疑問を持っているなら、無料サンプルを体験することができます。このサンプルの利用を通して、お客様は弊社の商品に自信を持って、安心で試験を準備することができます。