質問 1:RFT, an engineering company, has been asked to provide a quotation for a contract to build a new engine. The potential customer is not a current customer of RFT, but the directors of RFT are keen to try and win the contract as they believe that this may lead to more contracts in the future. As a result, they intend pricing the contract using relevant costs. The following information has been obtained from a two-hour meeting that the Production Director of RFT had with the potential customer. The Production Director is paid an annual salary equivalent to $1,200 per 8-hour day. 110 square meters of material A will be required. This is a material that is regularly used by RFT and there are 200 square meters currently in inventory. These were bought at a cost of $12 per square meter. They have a resale value of
$10.50 per square meter and their current replacement cost is $12.50 per square meter. 30 liters of material B will be required. This material will have to be purchased for the contract because it is not otherwise used by RFT. The minimum order quantity from the supplier is 40 liters at a cost of $9 per liter. RFT does not expect to have any use for any of this material that remains after this contract is completed. 60 components will be required. These will be purchased from HY. The purchase price is $50 per component. A total of 235 direct labour hours will be required. The current wage rate for the appropriate grade of direct labour is $11 per hour. Currently RFT has 75 direct labour hours of spare capacity at this grade that is being paid under a guaranteed wage agreement. The additional hours would need to be obtained by either (i) overtime at a total cost of $14 per hour; or (ii) recruiting temporary staff at a cost of $12 per hour. However, if temporary staff are used they will not be as experienced as RFT's existing workers and will require 10 hours supervision by an existing supervisor who would be paid overtime at a cost of $18 per hour for this work. 25 machine hours will be required.
The machine to be used is already leased for a weekly leasing cost of $600. It has a capacity of 40 hours per week. The machine has sufficient available capacity for the contract to be completed. The variable running cost of the machine is $7 per hour. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.
Select ALL the true statements.
A. The cost for the production director meeting was a relevant cost.
B. The relevant cost is $7080
C. The relevant cost is $7100
D. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.
This is a relevant cost.
E. The machine is currently being leased and it has spare capacity so it will either stand idle or be used on this work. The lease cost will be a relevant cost or $10 per hour.
F. The relevant cost is $7010
G. Material A was a relevant cost.
H. The components are to be purchased from HY at a cost of $50 each. This is a relevant cost because it is future expenditure that will be incurred as a result of the work being undertaken.
I. Material B was a relevant cost.
正解:F,G,H,I
質問 2:A company makes and sells three products A, B and C. The products are sold in the ratio of A:B:C = 1:1:4.
Monthly fixed costs are $150,000. Product details are shown below:

What sales value of product C is required to achieve a target profit of $72,000 next month?
Give your answer to the nearest whole $ (in '000s).
正解:
270000
質問 3:A completed unit of Product A requires 9 kg of material and 10% of material is wasted in the production process.
Material has a standard cost of $5 per kg.
Product A also requires 4 labour hours at a standard cost of $10 per labour hour and variable overheads at a standard cost of $2 per labour hour What is the standard variable production cost per unit of Product A?
A. $93
B. $98
C. $97.50
D. $50
正解:B
質問 4:Place the type of budget or cost against its definition.
正解:
質問 5:Explain the advantages of management participation in budget setting and the potential problems that may arise in the use of the resulting budget as a control mechanism.
Select all the correct answers.
A. Participation in budget setting can cause problems; in particular, managers may attempt to negotiate budgets that they feel are easy to achieve which gives rise to "budget padding" or budgetary slack.
B. Another purpose of a budget is to set targets to motivate managers and optimize their performance.
C. Participation in budget setting can reduce the information asymmetry gap that can arise when targets are imposed by senior management. Imposed targets are likely to make managers feel demotivated and alienated and result in poor performance.
D. A purposes of budgeting is to act as a control mechanism, with actual results being compared against budget.
E. The participation of managers in the budget setting process has several advantages. Managers are more likely to be motivated to achieve the target if they have participated in setting process has several advantages. managers are more likely to be motivated to achieve the target if they have participated in setting the target.
F. Managers will not 'empire build' because they don't believe that the size of their budget reflects their importance within the organization.
正解:A,B,C,D,E
質問 6:A manufacturing company has more units of finished goods inventory at the end of a period than at the beginning of the period.
Which of the following statements is true?
A. Profit is higher and opening inventory valuation is lower using absorption costing than if marginal costing is used.
B. Profit is higher and opening inventory valuation is higher using marginal costing than if throughput costing is used.
C. Profit is higher and opening inventory valuation is lower using marginal costing than if throughput costing is used.
D. Profit is lower and opening inventory valuation is higher using marginal costing than if throughput costing is used.
正解:B
質問 7:A manager must select one of three projects, W, X or Y.
The following payoff table has been prepared to show the outcomes in $000 at three possible levels of demand:

The manager is now preparing a regret matrix.
What figure (in $000) will be shown for Project Y in the regret matrix if the average demand arises?
A. 160
B. 150
C. 110
D. 520
正解:B
質問 8:XY sells two products for which the budgeted contribution to sales ratios are as follows:

Total budgeted sales revenue is $920,000, of which $368,000 will be generated by product X. The products must be sold in a constant mix.
Budgeted fixed costs are $105,000.
What is the budgeted breakeven sales revenue?
Give your answer to the nearest $.
正解:
$500000
質問 9:TP makes wedding cakes that are sold to specialist retail outlets which decorate the cakes according to the customers' specific requirements. The standard cost per unit of its most popular cake is as follows:

The general market prices at the time of purchase for Ingredient A and Ingredient B were $23 per kg and
$20 per kg respectively.
TP operates a JIT purchasing system for ingredients and a JIT production system; therefore, there was no inventory during the period.
Prepare a statement which reconciles the flexed budget material cost and the actual material cost. Your statement should include the material price planning variances, and the operational variances including material price, material mix and material yield.
What was the material price planning variance for ingredient A?
A. The Material price planning variance - Ingredient A was $73 000 F
B. The Material price planning variance - Ingredient A was $75 000 F
C. The Material price planning variance - Ingredient A was $71 000 F
D. The Material price planning variance - Ingredient A was $72 000 F
正解:D
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のCIMAPRO19-P01-1問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
弊社は無料CIMA CIMAPRO19-P01-1サンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料CIMAPRO19-P01-1サンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのCIMAPRO19-P01-1問題集は自分に適するかどうか判断して購入を決めることができます。
CIMAPRO19-P01-1試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
弊社は失敗したら全額で返金することを承諾します
我々は弊社のCIMAPRO19-P01-1問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のCIMA CIMAPRO19-P01-1を利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
CIMA CIMAPRO19-P01-1 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Determine the activity that causes the change in cost
- Understand the difference between variable costs and fixed costs
|
トピック 2 | - Understand the impact of individuals’ risk attitudes on decision-making in the short term
- Understand the difference between direct costs and indirect costs
|
トピック 3 | - Calculate subdivision of total usage
- efficiency variances into mix and yield variances
- Use material, labour, variable overhead, fixed overhead and sales variances
|
トピック 4 | - Calculate the breakeven point and output level required to meet income targets
- Understand costing and the different reasons for calculating costs
|
トピック 5 | - Establish manufacturing standards for material, labour, variable overhead and fixed overhead
- Understand the difference between financial accounting and cost accounting
|
トピック 6 | - Understand relevant cash flows and non-financial factors and how it affects make or buy decisions
- Understand the strategic implications of short-term decision-making
|
トピック 7 | - Calculate revenue and cost estimates using quantitative analyses
- Calculate and interpret overall flexed budget variances
|
参照:https://www.cimaglobal.com/Qualifications/Professional-Qualification/Operational-level/
TopExamは君にCIMAPRO19-P01-1の問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。
一年間の無料更新サービスを提供します
君が弊社のCIMA CIMAPRO19-P01-1をご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたCIMA CIMAPRO19-P01-1をお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のCIMA CIMAPRO19-P01-1を持っていることを保証します。
弊社のCIMA CIMAPRO19-P01-1を利用すれば試験に合格できます
弊社のCIMA CIMAPRO19-P01-1は専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はCIMAPRO19-P01-1問題集の質問と答えが間違いないのを保証いたします。

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のCIMA CIMAPRO19-P01-1を利用すれば、君は一回で試験に合格できます。