HACKER SAFEにより証明されたサイトは、99.9%以上のハッカー犯罪を防ぎます。
カート(0

AACE International CCP 問題集

CCP

試験コード:CCP

試験名称:Certified Cost Professional (CCP) Exam

最近更新時間:2025-04-09

問題と解答:全189問

CCP 無料でデモをダウンロード:

PDF版 Demo ソフト版 Demo オンライン版 Demo

追加した商品:"PDF版"
価格: ¥6599 

無料問題集CCP 資格取得

質問 1:
How can the quality of a cost/capacity factor estimate be improved?
A. Validate law productivity from recently completed projects
B. Validate the capacity factor from similar, recently completed projects
C. Verify the labor rates used in the estimate
D. Verify the equipment costs used in the estimate
正解:B
解説: (Topexam メンバーにのみ表示されます)

質問 2:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?
A. Update the remaining duration for each activity
B. Recalculate the critical path
C. Recalculate the early finish for each activity
D. Recalculate the early start for each activity
正解:A
解説: (Topexam メンバーにのみ表示されます)

質問 3:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Why is a +/- notation necessary when developing an estimate?
A. Contingency cushion
B. There are unknowns that affect the final cost of a project
C. It makes up for the lack of time to develop a real estimate
D. It is a government requirement
正解:B
解説: (Topexam メンバーにのみ表示されます)

質問 4:
A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:
A. Performance bond
B. Surety bond
C. Bid bond
D. Liability bond
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 5:
After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.
After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.
Is the percent complete stated by the contractor correct?
A. No, it should be 52.5%
B. Yes, it is 60%
C. No, it should be 55.0%
D. No, it should be 50.0%
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 6:
The process of stating goals and determining the most effective way of reaching them is the definition for:
A. Mission Statement
B. Planning
C. Managing
D. Implementing
正解:B
解説: (Topexam メンバーにのみ表示されます)

質問 7:
After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.
How does the project stand?
A. Schedule is good, cost is bad
B. Schedule is bad, cost is bad
C. Schedule is bad cost is good
D. Schedule is good cost is good
正解:C
解説: (Topexam メンバーにのみ表示されます)

質問 8:
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?
A. 6,960
B. 6,600
C. 7,200
D. 6,573
正解:B
解説: (Topexam メンバーにのみ表示されます)

質問 9:
A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required?
A. 3.5 cubic yards
B. 3.0 cubic yards
C. 2.5 cubic yards
D. 2.0 cubic yards
正解:D
解説: (Topexam メンバーにのみ表示されます)

弊社のAACE International CCPを利用すれば試験に合格できます

弊社のAACE International CCPは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はCCP問題集の質問と答えが間違いないのを保証いたします。

CCP無料ダウンロード

この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のAACE International CCPを利用すれば、君は一回で試験に合格できます。

安全的な支払方式を利用しています

Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のCCP問題集は全部Credit Cardで支払われることができます。

領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。

弊社は無料AACE International CCPサンプルを提供します

お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料CCPサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのCCP問題集は自分に適するかどうか判断して購入を決めることができます。

CCP試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。

TopExamは君にCCPの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。

弊社は失敗したら全額で返金することを承諾します

我々は弊社のCCP問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のAACE International CCPを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。

AACE International CCP 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Cost Estimating: This section focuses on diverse estimating methodologies, techniques, cost evaluation, and effective management of cost data to ensure precise project estimates.
トピック 2
  • Cost Control: In this section, candidates are tested for skills related to budgeting, forecasting, cost management techniques like EVM, handling scope changes, and evaluating cost-related risks and performance metrics.
トピック 3
  • Planning and Scheduling: This section covers project planning, resource management, scheduling strategies, and approaches for monitoring, controlling, and assessing schedule risks.

参照:https://web.aacei.org/certification/certification-information/certifications-offered/professional-certifications/ccp-details

一年間の無料更新サービスを提供します

君が弊社のAACE International CCPをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたAACE International CCPをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のAACE International CCPを持っていることを保証します。

CCP 関連試験
AACE-PSP - Planning & Scheduling Professional (PSP) Exam
連絡方法  
 [email protected] サポート

試用版をダウンロード

人気のベンダー
Apple
Avaya
CIW
FileMaker
Lotus
Lpi
OMG
SNIA
Symantec
XML Master
Zend-Technologies
The Open Group
H3C
3COM
ACI
すべてのベンダー
TopExam問題集を選ぶ理由は何でしょうか?
 品質保証TopExamは我々の専門家たちの努力によって、過去の試験のデータが分析されて、数年以来の研究を通して開発されて、多年の研究への整理で、的中率が高くて99%の通過率を保証することができます。
 一年間の無料アップデートTopExamは弊社の商品をご購入になったお客様に一年間の無料更新サービスを提供することができ、行き届いたアフターサービスを提供します。弊社は毎日更新の情況を検査していて、もし商品が更新されたら、お客様に最新版をお送りいたします。お客様はその一年でずっと最新版を持っているのを保証します。
 全額返金弊社の商品に自信を持っているから、失敗したら全額で返金することを保証します。弊社の商品でお客様は試験に合格できると信じていますとはいえ、不幸で試験に失敗する場合には、弊社はお客様の支払ったお金を全額で返金するのを承諾します。(全額返金)
 ご購入の前の試用TopExamは無料なサンプルを提供します。弊社の商品に疑問を持っているなら、無料サンプルを体験することができます。このサンプルの利用を通して、お客様は弊社の商品に自信を持って、安心で試験を準備することができます。