質問 1:Resources are limited. The Sales Manager has two marketing assistants who may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
A. Make each Timebox as long as possible to ensure the marketing
assistants have enough time to complete any work allocated to them
within the boundaries of the Timebox.
B. Schedule the two marketing assistants to work at different times so they can hand matters over to one another.
C. Accept that members of the Solution Development Team will be
inconsistent.
D. Try to secure formal agreement as to how many hours per week the
marketing assistants will spend on the project.
正解:D
解説: (Topexam メンバーにのみ表示されます)
質問 2:During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox.
The Project Manager organised a Facilitated Workshop to re-
engage this group and explore discrepancies in understanding.
Is this an appropriate application of Agile Project Management for this project?
A. Yes, because discussing requirements in the presence of other stakeholders increases the whole group's awareness.
B. Yes, because Facilitated Workshops provide a forum for each member of the team to present a short progress report.
C. No, because the local Action Group should have attended the Daily Stand-up meetings.
D. No, because the Project Manager should have escalated this disagreement as an issue before any action was taken.
正解:A
質問 3:Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E. that applies. Each option can be used once, more than once or not at all.
正解:
Explanation:
The activities from Column 1 should be performed in the following steps from Column 2, according to the iterative development process:
* Create the data entry screen for entering coffee bar details needed for a quotation.Selection: B.
ActionExplanation: Creating the data entry screen is part of the 'Action' step in iterative development, where the actual product or a part of it is being constructed.
* Enter numbers into a text-only field to see how the web page behaves.Selection: A. Thought Explanation: Testing how the web page behaves by entering data is part of the 'Thought' step, which includes reviewing and evaluating the work done, testing, and reflecting on the outcomes.
* Discuss the requirements of the new coffee bar insurance web page and agree which data fields are important.Selection: C. ConversationExplanation: Discussing and agreeing on the requirements is part of the 'Conversation' step, which involves interactions between team members and stakeholders to understand and define what needs to be built.
質問 4:Which 2 actions should the Project Manager take to implement the new Must Have requirement?
A. Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
B. Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
C. Consolidate and circulate an agenda for the workshop.
D. Source and hire a web developer with experience in developing online financial transaction functionality.
E. Check for any documented standards which need to be applied to the development of online financial transaction functionality.
正解:A,B
解説: (Topexam メンバーにのみ表示されます)
質問 5:Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the Solution Development Team are all based in this office but work at different ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective collaboration of the Solution Development Team?
A. Relocate these employees to a new project area, with a number of desks where the Solution Development Team can sit together.
B. Create an email group for the Solution Development Team to collaborate on ideas.
C. Set up a telephone or video conferencing facility so that all members of the team can collaborate effectively.
D. No action required as these employees are located in the same office.
正解:A
解説: (Topexam メンバーにのみ表示されます)
質問 6:Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox Plan for Timebox B?
A. Marketing Director, in the role of Business Visionary.
B. Architecture Angels' Senior Management Team.
C. Team Leader.
D. Project Manager and Architect, in the role of Technical Co-ordinator.
正解:C
APMG-International AgilePM-Practitioner 認定試験の出題範囲:
トピック | 出題範囲 |
---|
トピック 1 | - Techniques: In this section, the topics covered various techniques that can be utilized including iterative development. Candidates are tested for their know-how of agile techniques and timeboxing.
|
トピック 2 | - People and Roles: In this section, the topics covered include various roles involved in an Agile project and how they relate to each other. The topics covered include the responsibilities of the Agile Project Manager, agile teams, and business owners.
|
トピック 3 | - Lifecycle and Products: This section of the exam covers topics such as Agile project lifecycle, various stages of the lifecycle, agile products, Vision Documents, and Prototypes.
|
トピック 4 | - Planning and Control: In this section, the exam covers planning and control of the project and vital concepts such as estimation and iterative strategy. It also covers how to utilize MoSCoW prioritization and mitigate any risks.
|
参照:https://apmg-international.com/product/agile-project-management-agilepmr-certification
一年間の無料更新サービスを提供します
君が弊社のAPMG-International AgilePM-Practitionerをご購入になってから、我々の承諾する一年間の更新サービスが無料で得られています。弊社の専門家たちは毎日更新状態を検査していますから、この一年間、更新されたら、弊社は更新されたAPMG-International AgilePM-Practitionerをお客様のメールアドレスにお送りいたします。だから、お客様はいつもタイムリーに更新の通知を受けることができます。我々は購入した一年間でお客様がずっと最新版のAPMG-International AgilePM-Practitionerを持っていることを保証します。
TopExamは君にAgilePM-Practitionerの問題集を提供して、あなたの試験への復習にヘルプを提供して、君に難しい専門知識を楽に勉強させます。TopExamは君の試験への合格を期待しています。
弊社は失敗したら全額で返金することを承諾します
我々は弊社のAgilePM-Practitioner問題集に自信を持っていますから、試験に失敗したら返金する承諾をします。我々のAPMG-International AgilePM-Practitionerを利用して君は試験に合格できると信じています。もし試験に失敗したら、我々は君の支払ったお金を君に全額で返して、君の試験の失敗する経済損失を減少します。
安全的な支払方式を利用しています
Credit Cardは今まで全世界の一番安全の支払方式です。少数の手続きの費用かかる必要がありますとはいえ、保障があります。お客様の利益を保障するために、弊社のAgilePM-Practitioner問題集は全部Credit Cardで支払われることができます。
領収書について:社名入りの領収書が必要な場合、メールで社名に記入していただき送信してください。弊社はPDF版の領収書を提供いたします。
弊社は無料APMG-International AgilePM-Practitionerサンプルを提供します
お客様は問題集を購入する時、問題集の質量を心配するかもしれませんが、我々はこのことを解決するために、お客様に無料AgilePM-Practitionerサンプルを提供いたします。そうすると、お客様は購入する前にサンプルをダウンロードしてやってみることができます。君はこのAgilePM-Practitioner問題集は自分に適するかどうか判断して購入を決めることができます。
AgilePM-Practitioner試験ツール:あなたの訓練に便利をもたらすために、あなたは自分のペースによって複数のパソコンで設置できます。
弊社のAPMG-International AgilePM-Practitionerを利用すれば試験に合格できます
弊社のAPMG-International AgilePM-Practitionerは専門家たちが長年の経験を通して最新のシラバスに従って研究し出した勉強資料です。弊社はAgilePM-Practitioner問題集の質問と答えが間違いないのを保証いたします。
この問題集は過去のデータから分析して作成されて、カバー率が高くて、受験者としてのあなたを助けて時間とお金を節約して試験に合格する通過率を高めます。我々の問題集は的中率が高くて、100%の合格率を保証します。我々の高質量のAPMG-International AgilePM-Practitionerを利用すれば、君は一回で試験に合格できます。